When working with projects, you can enter budgets for each project, broken down by cost code. You can then use the Enquiry option to analyse the actual costs against budgets for each project, cost type and cost code. Let's take a look.
NOTE: This functionality is only available in the professional variant of the software. Need to upgrade? - Submit your details and we'll be in touch.
On the navigation bar click Projects, click the required project then click Enquiry.
| Project Reference and Name | The project reference and name appear here. If the project has any sub-projects, to view these, click the plus sign to the left of the Name.![]() |
|---|---|
| View Type | Choose to view the project structure by name or by reference. |
| Actual | Total value of all cost postings for the project. |
| Committed | Total value of all committed cost postings for the project. |
| Budget | Total budget for the project. |
| Variance | Calculates as Budget - Actual. If the Include committed costs in variances check box is selected, this calculates as Budget - (Actual + Committed). |
| Include committed costs in variances | To include committed costs in the Variance figure, select this check box. |

| Project Reference and Name | The project reference and name appear here. If the project has any sub-projects, you can use the plus sign to the left of the Name or Reference to view the sub-projects.
|
|---|---|
| Actual | Total value of all cost postings for the project. |
| Committed | Total value of all committed cost postings for the project. |
| Budget | Total budget for the project. |
| Variance | Calculates as Budget - Actual. If the Include committed costs in variances check box is selected, this calculates as Budget - (Actual + Committed). |
| Include sub projects> | To include the values for all sub projects, select this check box. |
| Include committed costs in variances | To include committed costs in the Variance figure, select this check box. |

| Project Reference and Name | The project reference and name appear here. If the project has any sub-projects, you can use the plus sign to the left of the Name or Reference to view the sub-projects.![]() |
|---|---|
| Cost Type | Choose the cost type to want to see. |
| Actual | Total value of all cost postings for the project. |
| Committed> | Total value of all committed cost postings for the project. |
| Budget | Total budget for the project. |
| Variance | Calculates as Budget - Actual. If the Include committed costs in variances check box is selected, this calculates as Budget - (Actual + Committed). |
| Include sub projects | To include the values for all sub projects, select this check box. |
| Include committed costs in variances | To include committed costs in the Variance figure, select this check box. |