Cost Codes When you enter transactions such as supplier invoices, for a project, you must associate a Cost Code. Use Cost Codes to identify the costs that a project incurs, for example, the materials to create a product or the labour for a job. For example, to summarise overheads, use the default OHD1 Cost Code to group them. If you want more detailed analysis, set up separate Cost Codes for each overhead type. For example, electricity, water, and gas. Assigning cost types to these codes lets you break down overheads accurately while still analysing them in total. By default, the following four cost codes are available: - LAB1 (Labour Charges)
- MAT 1 (Material Charges)
- OHD 1 (Overheads)
- MIX 1 (Mixed)
A Cost Code can belong to one Cost Type only. You can create up to 99 different Cost Codes. ▼ Create a Cost Code - Go to Settings, select Configuration, then Project Costing.
- In the Cost Codes section, click Add Code.
- Complete the Add Cost Code window as follows:
Code | Enter the required Cost Code. | Description | Enter a description for the Cost Code. | Cost Type | Choose the Cost Type to which the Cost Code belongs. | Any transactions that you enter to this Cost Code will also allocate to the chosen Cost Type. - Click OK then click OK to close the Configuration Editor.
Cost Types Each Cost Code has a Cost Type, making it easy to track and analyse project expenses. This helps group similar costs together for better reporting.  For example, you could categorise cost codes for electricity, water, gas, and rent under OVERHEADS. By default the following cost type are available: - LABOUR
- MATERIALS
- OVERHEADS
- MIXED
- OTHER
When you enter a project transaction, you need to enter a Cost Code to affect a Cost Type. You can create up to 99 different Cost Types. ▼ Create a Cost Type You can create up to 99 different Cost Types. - Go to Settings, select Configuration, then Project Costing.
- In the Cost Type section, click Add Type.
- Enter the required Name then click OK.
- Click OK to close the Configuration Editor.
Next steps Use our Project cost codes and cost types reports article to print a list of Cost Codes or run other reports. [BCB:19:UK - Sales message :ECB] |